There hasn't been significant updates to the site compared to earlier weeks. No tiling discussion happened yet, and no sign of tile delivery on site.
Cupboards and shelves have been installed both in kitchen and butler's pantry. And the colours look good. We had chosen
Belgian Oak Matt and
Marni Lini Matt from Polytec respectively for under-bench cupboards and overhead cupboards & shelves. Here is how it looks:
|
Cordova Two: Cupboards in Belgian Oak and Marni Lini Matt |
|
Cordova Two: Cupboards in Belgian Oak and Marni Lini Matt |
I am sure these cupboards are so waiting for the
Caesarstone Linen benchtop :)
Shower hobs have been installed and vanity installation is in progress:
The laundry linen door mistake has been rectified though it doesn't look well-corrected (see the right side of the frame): Now we know why it took only half-an-hour to correct it!
|
Cordova Two: Laundry |
Initially it was placed like this:
|
Cordova Two: Laundry |
Apart from these, the holes for down-lights, electrical outlets have been cut in Gyprock.
Now eagerly waiting for Tiling updates so that we can proceed with wet area tiling.
PS: Got to know from our SS today that tiles will be delivered on Tuesday afternoon and tilers will be working (i.e. screeding) on site from Wednesday morning. We plan to visit on Thursday though for our Tiling discussion.